LX0-104 · Question #156
Which of the following resources would be measured for capacity planning? (Select TWO correct answers.)
The correct answer is A. CPU usage D. memory usage. For effective capacity planning, key system resources such as CPU usage and memory usage are essential metrics to measure.
Question
Options
- ACPU usage
- Bdisk usage
- Capplication load time
- Dmemory usage
How the community answered
(18 responses)- A89% (16)
- B6% (1)
- C6% (1)
Why each option
For effective capacity planning, key system resources such as CPU usage and memory usage are essential metrics to measure.
CPU usage is a fundamental metric for capacity planning as it indicates the processing power demand of applications and overall system workload, helping to determine if current CPU resources are sufficient or if an upgrade is needed.
Disk usage (storage space) is important for capacity planning of storage capacity, but the question is about 'resources' in the context of system performance and processing, where CPU and RAM are primary for real-time operations.
Application load time is a performance metric reflecting user experience or application startup duration, not a core system resource that is directly measured for hardware capacity planning in the same way as CPU or memory.
Memory usage, specifically physical RAM consumption, is crucial for capacity planning because it reflects the working set of applications and helps assess whether the system has adequate RAM to prevent excessive swapping and maintain performance.