The correct answer is B. An audit program outlines the overarching framework for a series of audits with specific timelines. See the full explanation below for the reasoning.
Question
What is the main difference between an audit program and an audit plan?
Options
- AAn audit program outlines the activities and arrangements for a particular audit, while an audit
- BAn audit program outlines the overarching framework for a series of audits with specific timelines
- CAn audit program outlines policies, procedures, or requirements for reference in audit evidence