A manufacturing company faced a risk of production delays due to potential supply chain disruptions. After assessing the potential impact of the risk, the company decided to accept the risk…
The correct answer is B. Risk retention. See the full explanation below for the reasoning.
Question
A manufacturing company faced a risk of production delays due to potential supply chain disruptions. After assessing the potential impact of the risk, the company decided to accept the risk, considering the disruption unlikely to significantly affect its operations. Which risk treatment option did the company select in this case?
Options
- ARisk avoidance
- BRisk retention
- CRisk deflection
How the community answered
(69 responses)- A19% (13)
- B71% (49)
- C10% (7)