Scenario: A manufacturing company faced a risk of production delays due to potential supply chain disruptions. After assessing the potential impact, the company concluded the disruption was unlikely…
The correct answer is B. Risk retention. See the full explanation below for the reasoning.
Question
Scenario:
A manufacturing company faced a risk of production delays due to potential supply chain disruptions. After assessing the potential impact, the company concluded the disruption was unlikely to significantly affect operations. The company decided to accept the risk. Which risk treatment option did the company select in this case?
Options
- ARisk avoidance
- BRisk retention
- CRisk deflection
How the community answered
(38 responses)- A8% (3)
- B76% (29)
- C16% (6)