LEAD-IMPLEMENTER · Question #107
Following a repotted event, an Information security event ticket has been completed and its priority has been assigned. Then, the event has been evaluated to determine. If it is an information…
The correct answer is C. Evaluation and confirmation. See the full explanation below for the reasoning.
Question
Following a repotted event, an Information security event ticket has been completed and its priority has been assigned. Then, the event has been evaluated to determine. If it is an information security incident, which phase of the incident management has been completed?
Options
- Ainitial assessment and decision
- BDetection and reporting
- CEvaluation and confirmation
How the community answered
(50 responses)- A16% (8)
- B8% (4)
- C76% (38)