When using change-control processes, which three actions must be considered? (Choose three.)
The correct answer is A. Coordinate scheduling that will be least impactful to production. D. Formalize the request based on company policies. E. Balance troubleshooting needs with productions risks. See the full explanation below for the reasoning.
Question
When using change-control processes, which three actions must be considered? (Choose three.)
Options
- ACoordinate scheduling that will be least impactful to production.
- BCoordinate scheduling that works best with the individuals involved.
- CPerform testing in a production environment prior to change-control.
- DFormalize the request based on company policies.
- EBalance troubleshooting needs with productions risks.
How the community answered
(29 responses)- A72% (21)
- B10% (3)
- C17% (5)
Community Discussion