The network team will be performing maintenance on R3. The maintenance window requires a reboot of router R3. You want to gracefully move traffic away from R3 until after the reboot. In this…

The correct answer is B. Configure the set protocols isis overload parameter, then commit the configuration. See the full explanation below for the reasoning.

Question

The network team will be performing maintenance on R3. The maintenance window requires a reboot of router R3. You want to gracefully move traffic away from R3 until after the reboot. In this scenario, how would you solve this problem?

Options

  • AConfigure the set protocols isis interface all level 1 hold-time 300 parameter, then reboot the
  • BConfigure the set protocols isis overload parameter, then commit the configuration.
  • CConfigure the set protocols isis spf-options delay 300 parameter, then reboot the router.
  • DConfigure the set protocols isis interface all level 1 hello-interval 300 parameter, then reboot the

How the community answered

(15 responses)
  • B
    80% (12)
  • C
    13% (2)
  • D
    7% (1)