A customer on MSTI-2 was isolated due to a physical link outage on Switch 5's ge-0/0/32 interface. Referring to the exhibit, which corrective action would solve this problem?

The correct answer is D. Add MSTI-2 to all interfaces on Switch 5. See the full explanation below for the reasoning.

Question

A customer on MSTI-2 was isolated due to a physical link outage on Switch 5's ge-0/0/32 interface. Referring to the exhibit, which corrective action would solve this problem?

Exhibit

JN0-648 question #74 exhibit

Options

  • Areplace the link between Switch 5 and 6 with a 10 Gbps link
  • BImplement the CIST on all switches.
  • CMove the root bridge for MSTI-2 to Switch 6.
  • DAdd MSTI-2 to all interfaces on Switch 5.

How the community answered

(53 responses)
  • A
    8% (4)
  • B
    4% (2)
  • C
    15% (8)
  • D
    74% (39)