A customer on MSTI-2 was isolated due to a physical link outage on Switch 5's ge-0/0/32 interface. Referring to the exhibit, which corrective action would solve this problem?
The correct answer is D. Add MSTI-2 to all interfaces on Switch 5. See the full explanation below for the reasoning.
Question
A customer on MSTI-2 was isolated due to a physical link outage on Switch 5's ge-0/0/32 interface. Referring to the exhibit, which corrective action would solve this problem?
Exhibit
Options
- Areplace the link between Switch 5 and 6 with a 10 Gbps link
- BImplement the CIST on all switches.
- CMove the root bridge for MSTI-2 to Switch 6.
- DAdd MSTI-2 to all interfaces on Switch 5.
How the community answered
(53 responses)- A8% (4)
- B4% (2)
- C15% (8)
- D74% (39)