Which three actions must be taken prior to deploying an IDP Sensor in a network? (Choose three.)

The correct answer is B. IDP Sensor must be configured with the ACM and assigned a Management IP address. C. A Security Policy must be configured for this IDP Sensor. D. The IDP Sensor object must be configured in the IDP Management Server. See the full explanation below for the reasoning.

Question

Which three actions must be taken prior to deploying an IDP Sensor in a network? (Choose three.)

Options

  • AAn IP address must be defined on all forwarding interfaces.
  • BIDP Sensor must be configured with the ACM and assigned a Management IP address.
  • CA Security Policy must be configured for this IDP Sensor.
  • DThe IDP Sensor object must be configured in the IDP Management Server.

How the community answered

(25 responses)
  • A
    20% (5)
  • B
    80% (20)

Community Discussion

No community discussion yet for this question.