Which command is used to verify IKE Phase 1 is complete?
The correct answer is C. Get ike cookie. See the full explanation below for the reasoning.
Question
Which command is used to verify IKE Phase 1 is complete?
Options
- AGet ike active
- BGet sa a active
- CGet ike cookie
- DGet flow active
How the community answered
(28 responses)- A7% (2)
- B11% (3)
- C79% (22)
- D4% (1)