JN0-481 · Question #38
You want to assign resources to your blueprint during the deployment phase. In this scenario, which statement is correct?
The correct answer is B. To assign resources in the blueprint, you must have already created them under global resources. To assign resources to a blueprint in Juniper Apstra, the resources (such as IP pools, ASN pools, VLANs, etc.) must already be created under global resources. Once created, these global resources can then be allocated to the blueprint during the deployment phase.
Question
You want to assign resources to your blueprint during the deployment phase. In this scenario, which statement is correct?
Options
- ATo assign resources in the blueprint, you must have completed the device profile and device
- BTo assign resources in the blueprint, you must have already created them under global resources.
- CAll resources are created and assigned under the blueprint's resources tab.
- DAll resources are automatically assigned values from the available resource pools.
How the community answered
(20 responses)- A5% (1)
- B95% (19)
Explanation
To assign resources to a blueprint in Juniper Apstra, the resources (such as IP pools, ASN pools, VLANs, etc.) must already be created under global resources. Once created, these global resources can then be allocated to the blueprint during the deployment phase.
Topics
Community Discussion
No community discussion yet for this question.