When bringing up a QFX3000-M QFabric system control plane network, which three actions should be performed? (Choose three.)

The correct answer is B. Apply site-specific configuration to EX Series switches. C. Verify connectivity and state of LAG between EX Series switches. E. Power on the EX Series switches. See the full explanation below for the reasoning.

Question

When bringing up a QFX3000-M QFabric system control plane network, which three actions should be performed? (Choose three.)

Options

  • AConfirm data plane connections on EX Series switches are up.
  • BApply site-specific configuration to EX Series switches.
  • CVerify connectivity and state of LAG between EX Series switches.
  • DConfigure the network Node group.
  • EPower on the EX Series switches.

How the community answered

(48 responses)
  • A
    8% (4)
  • B
    79% (38)
  • D
    13% (6)