What must happen for QFabric system RVIs to become active?
The correct answer is B. An operational Layer 2 interface is associated with the RVI VLAN. See the full explanation below for the reasoning.
Question
What must happen for QFabric system RVIs to become active?
Options
- AA network Node group is configured on the RVI VLAN.
- BAn operational Layer 2 interface is associated with the RVI VLAN.
- CA server Node group is configured on the RVI VLAN.
- DA Layer 3 interface is configured on the RVI VLAN.
How the community answered
(47 responses)- A9% (4)
- B72% (34)
- C15% (7)
- D4% (2)