nerdexam
Juniper

JN0-363 · Question #16

Referring to the exhibit. Which two statements are correct about the information shown in the exhibit? (Choose two.)

The correct answer is A. The root bridge is reachable using the ge-0/0/14 interface. C. This switch has a bridge priority of 8k. The exhibit shows the output of the command show spanning-tree bridge, which provides information about the spanning tree status of the switch. From the output, we can see that the switch has a bridge ID different from the root ID, which implies that this switch is not the root…

High Availability

Question

Referring to the exhibit. Which two statements are correct about the information shown in the exhibit? (Choose two.)

Exhibit

JN0-363 question #16 exhibit

Options

  • AThe root bridge is reachable using the ge-0/0/14 interface.
  • BThis switch is the root bridge for this spanning tree topology.
  • CThis switch has a bridge priority of 8k.
  • DThe root bridge's priority Is 4k.

How the community answered

(44 responses)
  • A
    84% (37)
  • B
    5% (2)
  • D
    11% (5)

Explanation

The exhibit shows the output of the command show spanning-tree bridge, which provides information about the spanning tree status of the switch. From the output, we can see that the switch has a bridge ID different from the root ID, which implies that this switch is not the root bridge. The "Topology change initiator" field shows ge-0/0/14, which indicates that the last topology change occurred on this interface, and this is also the interface used to reach the root

Topics

#STP#root bridge#bridge priority#spanning tree topology

Community Discussion

No community discussion yet for this question.