In the exhibit, all switches run STP; however, the link between bridge G and bridge E fails. What does root bridge A do after it receives information about this link failure?
The correct answer is C. Root bridge A sets the topology change flag and sends an updated configuration BPDU. See the full explanation below for the reasoning.
Question
In the exhibit, all switches run STP; however, the link between bridge G and bridge E fails. What does root bridge A do after it receives information about this link failure?
Exhibit
Options
- ARoot bridge A sets the acknowledge flag and sends an updated topology BPDU.
- BRoot bridge A sends a topology change notification BPDU.
- CRoot bridge A sets the topology change flag and sends an updated configuration BPDU.
- DRoot bridge A floods an updated BPDU topology database.
How the community answered
(44 responses)- A9% (4)
- B2% (1)
- C84% (37)
- D5% (2)