nerdexam
Juniper

JN0-351 · Question #7

Which two statements about redundant trunk groups on EX Series switches are correct? (Choose two.)

The correct answer is B. If the active link fails, then the secondary link automatically takes over. C. Layer 2 control traffic is permitted on the secondary link. Redundant trunk groups are designed to provide link redundancy. If the primary link fails, the secondary link will automatically take over to ensure continued connectivity. In redundant trunk groups, while regular data traffic is sent over the primary link, Layer 2 control…

High Availability

Question

Which two statements about redundant trunk groups on EX Series switches are correct? (Choose two.)

Options

  • ARedundant trunk groups load-balance traffic across two designated uplink interfaces.
  • BIf the active link fails, then the secondary link automatically takes over.
  • CLayer 2 control traffic is permitted on the secondary link
  • DRedundant trunk groups must be connected to the same aggregation switch.

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    84% (38)
  • D
    11% (5)

Explanation

Redundant trunk groups are designed to provide link redundancy. If the primary link fails, the secondary link will automatically take over to ensure continued connectivity. In redundant trunk groups, while regular data traffic is sent over the primary link, Layer 2 control traffic (such as STP, LACP, etc.) is allowed on the secondary link to maintain network stability and protocol operations. map/redundant-trunk-groups.html

Topics

#redundant trunk groups#EX Series uplink#active-secondary failover#Layer 2 redundancy

Community Discussion

No community discussion yet for this question.

Full JN0-351 Practice