Juniper
JN0-343 · Question #137
Click the Exhibit button. You are deploying a Virtual Chassis consisting of four EX4200s. You have powered on all four switches at the same time with the settings shown in the exhibit. Which Virtual…
The correct answer is D. Switch-4. See the full explanation below for the reasoning.
Question
Click the Exhibit button. You are deploying a Virtual Chassis consisting of four EX4200s. You have powered on all four switches at the same time with the settings shown in the exhibit. Which Virtual Chassis member will become the master?
Exhibit
Options
- ASwitch-1
- BSwitch-2
- CSwitch-3
- DSwitch-4
How the community answered
(21 responses)- A5% (1)
- C10% (2)
- D86% (18)
Community Discussion
No community discussion yet for this question.