Juniper
JN0-332 · Question #273
You have been tasked with installing two SRX 5600 platforms in a high-availability cluster. Which requirement must be met for a successful installation?
The correct answer is C. You must ensure all SPCs use the same slot placement. See the full explanation below for the reasoning.
Question
You have been tasked with installing two SRX 5600 platforms in a high-availability cluster. Which requirement must be met for a successful installation?
Options
- AYou must enable SPC detect within the configuration.
- BYou must enable active-active failover for redundancy.
- CYou must ensure all SPCs use the same slot placement.
- DYou must configure auto-negotiation on the control ports of both devices.
How the community answered
(55 responses)- A4% (2)
- B13% (7)
- C76% (42)
- D7% (4)
Community Discussion
No community discussion yet for this question.