What are two considerations when performing a risk assessment for assets in a data center? (Choose two.)
The correct answer is A. Insurance is a viable mitigation strategy when performing risk assessment calculations D. Migration of a data center to a cloud provider reduces the economic impact of asset exposure. See the full explanation below for the reasoning.
Question
What are two considerations when performing a risk assessment for assets in a data center? (Choose two.)
Options
- AInsurance is a viable mitigation strategy when performing risk assessment calculations
- BExposure of assets could have larger economic impact man loss of assets
- CMigration of a data center to a cloud prouder increases economic impact of asset loss
- DMigration of a data center to a cloud provider reduces the economic impact of asset exposure
How the community answered
(21 responses)- A71% (15)
- B19% (4)
- C10% (2)