You are asked to develop a high-level design to meet a customer's requirement to transition an aging switched infrastructure to a newer approach, meeting their needs for the next five years. In your…
The correct answer is B. business costs of not going forward D. impact to the business from an operations perspective E. cost of the proposed solution. See the full explanation below for the reasoning.
Question
You are asked to develop a high-level design to meet a customer's requirement to transition an aging switched infrastructure to a newer approach, meeting their needs for the next five years. In your presentation to the IT department, which three areas are important to define? (Choose three.)
Options
- Arecommendations for IGP timers
- Bbusiness costs of not going forward
- Cconfiguration stanza for class of service definition
- Dimpact to the business from an operations perspective
- Ecost of the proposed solution
How the community answered
(30 responses)- A20% (6)
- B73% (22)
- C7% (2)