You are planning to add equipment into a data center environment. What are three physical environmental considerations? (Choose three.)

The correct answer is B. floor loading C. rack door positioning E. hot/cold aisle deployment. See the full explanation below for the reasoning.

Question

You are planning to add equipment into a data center environment. What are three physical environmental considerations? (Choose three.)

Options

  • AIP addressing
  • Bfloor loading
  • Crack door positioning
  • DVLAN assignments
  • Ehot/cold aisle deployment

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    73% (24)
  • D
    18% (6)