JK0-801 · Question #764

A technician is helping set up a new networking closet and notices that the humidity level is low in the room. Which of the following should be installed FIRST before rack mounting equipment?

The correct answer is D. Grounding bars. inefficient-data-centers/

Hardware

Question

A technician is helping set up a new networking closet and notices that the humidity level is low in the room. Which of the following should be installed FIRST before rack mounting equipment?

Options

  • AA dehumidifier
  • BA fire suppression system
  • CESD strap
  • DGrounding bars

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    15% (5)
  • C
    9% (3)
  • D
    70% (23)

Explanation

inefficient-data-centers/

Topics

#ESD protection#grounding#networking closet#static electricity