CompTIA
JK0-020 · Question #333
An administrator has received a request for a disaster recovery solution that will allow the company to bring the payroll system up within two to three weeks of a disaster being declared. Which of…
The correct answer is A. Cold site. See the full explanation below for the reasoning.
Question
An administrator has received a request for a disaster recovery solution that will allow the company to bring the payroll system up within two to three weeks of a disaster being declared. Which of the following would meet the MINIMUM requirements of this objective?
Options
- ACold site
- BWarm site
- CSatellite site
- DHot site
How the community answered
(19 responses)- A74% (14)
- B5% (1)
- C5% (1)
- D16% (3)
Community Discussion
No community discussion yet for this question.