JK0-019 Question #452: Real Exam Question with Answer & Explanation
The correct answer is A. Change management. See the full explanation below for the reasoning.
Question
A company has gone through several upgrades on their network but unfortunately have no way of identifying who approved the upgrades. Which of the following should be implemented to track this type of work?
Options
- AChange management
- BAsset management
- CAccess log
- DBaselines