The correct answer is C. Establish a plan of action. See the full explanation below for the reasoning.
Question
A home user states during a basement remodel, one of the workers cut the network cable that goes from the modem to the WAP and nothing else has changed. According to the network troubleshooting methodology, which of the following is the NEXT step?
Options
- AIdentify the problem
- BQuestion the user
- CEstablish a plan of action
- DEstablish a theory of probable cause