Upper management decides which risk to mitigate based on cost. This is an example of:

The correct answer is D. Quantitative risk assessment. See the full explanation below for the reasoning.

Question

Upper management decides which risk to mitigate based on cost. This is an example of:

Options

  • AQualitative risk assessment
  • BBusiness impact analysis
  • CRisk management framework
  • DQuantitative risk assessment

How the community answered

(49 responses)
  • A
    12% (6)
  • B
    4% (2)
  • C
    6% (3)
  • D
    78% (38)