CompTIA
JK0-018 · Question #501
Which of the following MOST specifically defines the procedures to follow when scheduled system patching fails resulting in system outages?
The correct answer is B. Change management. See the full explanation below for the reasoning.
Question
Which of the following MOST specifically defines the procedures to follow when scheduled system patching fails resulting in system outages?
Options
- ARisk transference
- BChange management
- CConfiguration management
- DAccess control revalidation
How the community answered
(54 responses)- A11% (6)
- B80% (43)
- C2% (1)
- D7% (4)
Community Discussion