Ann is starting a disaster recovery program. She has gathered specifics and team members for a meeting on site. Which of the following types of tests is this?

The correct answer is A. Structured walk through. See the full explanation below for the reasoning.

Question

Ann is starting a disaster recovery program. She has gathered specifics and team members for a meeting on site. Which of the following types of tests is this?

Options

  • AStructured walk through
  • BFull Interruption test
  • CCheck list test
  • DTable top exercise

How the community answered

(55 responses)
  • A
    78% (43)
  • B
    13% (7)
  • C
    5% (3)
  • D
    4% (2)