nerdexam
ISTQB

ISTQB-CTFL · Question #123

When should component integration tests be carried out?

The correct answer is D. Integration tests should always be done before system tests. Component integration tests are designed to verify the interactions and interfaces between integrated components. These tests should be carried out after component testing (where individual components are tested in isolation) but before system testing (where the entire system…

Testing Throughout the Software Development Lifecycle

Question

When should component integration tests be carried out?

Options

  • AIntegration tests should always be done after system tests
  • BIntegration tests should be done at the customer's site, after acceptance tests
  • CIntegration tests can be done before or after system tests
  • DIntegration tests should always be done before system tests

How the community answered

(31 responses)
  • B
    3% (1)
  • C
    3% (1)
  • D
    94% (29)

Explanation

Component integration tests are designed to verify the interactions and interfaces between integrated components. These tests should be carried out after component testing (where individual components are tested in isolation) but before system testing (where the entire system is tested as a whole). This ensures that any issues arising from the integration of components are identified and resolved early in the testing process, making option D the correct answer.

Topics

#integration testing#test levels#component integration#test ordering

Community Discussion

No community discussion yet for this question.

Full ISTQB-CTFL Practice