Scenario 8 (continued): Scenario 8: Scenario 8: InnovateSoft, headquartered in Berlin, Germany, is a software development company known for its innovative solutions and commitment to excellence. It…

The correct answer is A. Yes, it addressed all necessary aspects. The closing meeting covered: Uncertainty due to sampling Timeline for corrective actions Complaint and appeal procedures Findings and their classification These are all required elements of the closing meeting. ISO/IEC 17021-1:2015 Clause 9.4.7 requires the audit team to…

Audit Reporting and Closing

Question

Scenario 8 (continued):

Scenario 8:

Scenario 8: InnovateSoft, headquartered in Berlin, Germany, is a software development company known for its innovative solutions and commitment to excellence. It specializes in custom software solutions, development, design, testing, maintenance, and consulting, covering both mobile apps and web development. Recently, the company underwent an audit to evaluate the effectiveness and compliance of its artificial intelligence management system AIMS against ISO/IEC 42001. The audit team engaged with the auditee to discuss their findings and observations during the audit's final phases. After evaluating the evidence, the audit team presented their audit findings to InnovateSoft, highlighting the identified nonconformities. Upon receiving the audit findings, InnovateSoft accepted the conclusions but expressed concerns about some findings inaccurately reflecting the efficiency of their software development processes. In response, the company provided new evidence and additional information to alter the audit conclusions for a couple of minor nonconformities identified. After thorough consideration, the audit team leader clarified that the new evidence did not significantly alter the core conclusions drawn for the nonconformities. Therefore, the certification body issued a certification recommendation conditional upon the filing of corrective action plans without a prior visit. InnovateSoft accepted the decision of the certification body. The top management of the company also sought suggestions from the audit team on resolving the identified nonconformities. The audit team leader offered solutions to address the issues, fostering a collaborative effort between the auditors and InnovateSoft. During the closing meeting, the audit team covered key topics to enhance transparency. They clarified to InnovateSoft that the audit evidence was based on a sample, acknowledging the inherent uncertainty. The method and time frame of reporting and grading findings were discussed to provide a structured overview of nonconformities. The certification body's process for handling nonconformities, including potential consequences, guided InnovateSoft on corrective actions. The time frame for presenting a plan for correction was communicated, emphasizing urgency. Insights into the certification body's post-audit activities were provided, ensuring ongoing support. Lastly, the audit team briefed InnovateSoft on complaint and appeal handling. InnovateSoft submitted the action plans for each nonconformity separately, describing only the detected issues and the corrective actions planned to address the detected nonconformities. However, the submission slightly exceeded the specified period of 45 days set by the certification body, arriving three days later. InnovateSoft explained this by attributing the delay to unexpected challenges encountered during the compilation of the action plans. During the closing meeting, the audit team covered key topics including sampling uncertainty, timelines for corrections, and complaint/appeals procedures. Based on Scenario 8, was the concluding meeting comprehensive in addressing all essential components of the audit?

Options

  • AYes, it addressed all necessary aspects
  • BNo, it should not have involved the assessment of audit findings
  • CNo, it should not have involved the post-audit activities of the certification body

How the community answered

(32 responses)
  • A
    78% (25)
  • B
    6% (2)
  • C
    16% (5)

Explanation

The closing meeting covered: Uncertainty due to sampling Timeline for corrective actions Complaint and appeal procedures Findings and their classification These are all required elements of the closing meeting. ISO/IEC 17021-1:2015 Clause 9.4.7 requires the audit team to present a summary of findings and next steps during the closing meeting. ISO 19011:2018 Clause 6.6.12 further includes communication of audit conclusions, clarification of nonconformities, and how findings will be managed post-audit.

Topics

#closing meeting#audit findings assessment#post-audit activities#certification body

Community Discussion

No community discussion yet for this question.

Full ISO-IEC-42001-LEAD-AUDITOR Practice