ISO-IEC-42001-LEAD-AUDITOR · Question #67
A multinational technology corporation has initiated an audit process to assess compliance with ISO/IEC 42001. The audit team drafted an audit schedule after the initiation of the audit. Which…
The correct answer is C. The audit schedule is drafted after the initiation of the audit. An audit schedule must be prepared before the initiation of the audit. ISO/IEC 17021-1:2015 Clause 9.2.3.1 and ISO 19011:2018 Clause 6.4.3 require that the audit program and detailed schedule must be created prior to starting on-site activities. The ISO/IEC 42001 Lead Auditor…
Question
A multinational technology corporation has initiated an audit process to assess compliance with ISO/IEC 42001. The audit team drafted an audit schedule after the initiation of the audit. Which aspect of the audit schedule prepared by the audit team is NOT correct?
Options
- AThe audit schedule is based on a feasible time
- BThe audit schedule prioritizes tasks based on their significance and relevance
- CThe audit schedule is drafted after the initiation of the audit
How the community answered
(40 responses)- A8% (3)
- B18% (7)
- C75% (30)
Explanation
An audit schedule must be prepared before the initiation of the audit. ISO/IEC 17021-1:2015 Clause 9.2.3.1 and ISO 19011:2018 Clause 6.4.3 require that the audit program and detailed schedule must be created prior to starting on-site activities. The ISO/IEC 42001 Lead Auditor Guide notes: "The audit schedule must be planned and shared with the auditee during pre-audit activities."
Topics
Community Discussion
No community discussion yet for this question.