ISO-IEC-27001-LEAD-AUDITOR · Question #60

You are performing an ISMS initial certification audit at a residential nursing home that provides healthcare services. The next step in your audit plan is to conduct the closing meeting. During the…

The correct answer is D. Recommend certification after your approval of the proposed corrective action plan Recommend. According to ISO/IEC 17021-1:2015, which specifies the requirements for bodies providing audit and certification of management systems, clause 9.4.9 requires the certification body to make a certification decision based on the information obtained during the audit and any other…

Audit Findings and Conclusions

Question

You are performing an ISMS initial certification audit at a residential nursing home that provides healthcare services. The next step in your audit plan is to conduct the closing meeting. During the final audit team meeting, as an audit team leader, you agree to report 2 minor nonconformities and 1 opportunity for improvement as below:

Select one option of the recommendation to the audit programme manager you are going to advise to the auditee at the closing meeting.

Exhibit

ISO-IEC-27001-LEAD-AUDITOR question #60 exhibit

Options

  • ARecommend certification immediately
  • BRecommend that a full scope re-audit is required within 6 months
  • CRecommend that an unannounced audit is carried out at a future date
  • DRecommend certification after your approval of the proposed corrective action plan Recommend
  • ERecommend that a partial audit is required within 3 months

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    14% (4)
  • C
    7% (2)
  • D
    71% (20)
  • E
    4% (1)

Explanation

According to ISO/IEC 17021-1:2015, which specifies the requirements for bodies providing audit and certification of management systems, clause 9.4.9 requires the certification body to make a certification decision based on the information obtained during the audit and any other relevant information1. The certification body should also consider the effectiveness of the corrective actions taken by the auditee to address any nonconformities identified during the audit1. Therefore, when making a recommendation to the audit programme manager, an ISMS auditor should consider the nature and severity of the nonconformities and the proposed corrective actions. Based on the scenario above, the auditor should recommend certification after their approval of the proposed corrective action plan and recommend that the findings can be closed out at a surveillance audit in 1 year. The auditor should provide the following justification for their Justification: This recommendation is appropriate because it reflects the fact that the auditee has only two minor nonconformities and one opportunity for improvement, which do not indicate a significant or systemic failure of their ISMS. A minor nonconformity is defined as a failure to achieve one or more requirements of ISO/IEC 27001:2022 or a situation which raises significant doubt about the ability of an ISMS process to achieve its intended output, but does not affect its overall effectiveness or conformity2. An opportunity for improvement is defined as a suggestion for improvement beyond what is required by ISO/IEC 27001:20222. Therefore, these findings do not prevent or preclude certification, as long as they are addressed by appropriate corrective actions within a reasonable time frame. The auditor should approve the proposed corrective action plan before recommending certification, to ensure that it is realistic, achievable, and effective. The auditor should also recommend that the findings can be closed out at a surveillance audit in 1 year, to verify that the corrective actions have been implemented and are working as

Topics

#closing meeting#minor nonconformity#certification recommendation#corrective action plan