Which of the following is a MAJOR task of test planning?

The correct answer is A. Scheduling test analysis and design tasks. Scheduling test analysis and design tasks (A) is correct because test planning is fundamentally about defining what will be done, when, and by whom - scheduling activities like test design, environment setup, and execution is a core planning responsibility under ISTQB…

Test Management

Question

Which of the following is a MAJOR task of test planning?

Options

  • AScheduling test analysis and design tasks.
  • BInitiating corrective actions.
  • CMonitoring progress and test coverage.
  • DMeasuring and analyzing results.

How the community answered

(53 responses)
  • A
    77% (41)
  • B
    13% (7)
  • C
    6% (3)
  • D
    4% (2)

Explanation

Scheduling test analysis and design tasks (A) is correct because test planning is fundamentally about defining what will be done, when, and by whom - scheduling activities like test design, environment setup, and execution is a core planning responsibility under ISTQB guidelines.

Why the distractors are wrong:

  • B (Initiating corrective actions) belongs to test monitoring and control - you react to deviations from the plan, not plan for them upfront.
  • C (Monitoring progress and test coverage) is also a monitoring and control activity - tracking what's happening during execution, not planning.
  • D (Measuring and analyzing results) falls under test completion or evaluation activities, done after execution wraps up.

Memory tip: Think of planning as the "calendar and blueprint" phase - if it sounds like something you'd put on a project schedule before testing begins, it's planning. If it sounds like something you'd do during or after testing (watching, reacting, measuring), it belongs to monitoring/control or completion.

Topics