ISEB-SWTINT1 · Question #23
As part of which test process do you determine the exit criteria?
The correct answer is A. Test planning. Test planning (A) is where exit criteria are defined - this phase establishes what the testing will accomplish, including the conditions that must be met before testing can stop. Defining exit criteria upfront ensures the team has agreed-upon, measurable goals before work…
Question
Options
- ATest planning.
- BEvaluating exit criteria and reporting.
- CTest closure.
- DTest control.
How the community answered
(16 responses)- A75% (12)
- B6% (1)
- C13% (2)
- D6% (1)
Explanation
Test planning (A) is where exit criteria are defined - this phase establishes what the testing will accomplish, including the conditions that must be met before testing can stop. Defining exit criteria upfront ensures the team has agreed-upon, measurable goals before work begins.
B (Evaluating exit criteria and reporting) is wrong because this phase applies the criteria you already defined - it checks whether those conditions have been met, it doesn't create them.
C (Test closure) is wrong because closure happens after exit criteria are met; it's about wrapping up activities, archiving artifacts, and capturing lessons learned.
D (Test control) is wrong because control is an ongoing monitoring activity - comparing actual progress against the plan and taking corrective action - not a definitional phase.
Memory tip: Think of the word "planning" - you plan ahead. Exit criteria are the finish line, and you must draw the finish line before the race starts, not during or after it.