ISEB-BA1 · Question #96

Given the cashflows below, which of the following is correct?

The correct answer is B. The project does not pay back within the four year period. See the full explanation below for the reasoning.

Question

Given the cashflows below, which of the following is correct?

Exhibit

ISEB-BA1 question #96 exhibit

Options

  • AThe project pays back in year 4 of the project.
  • BThe project does not pay back within the four year period.
  • CThe project pays back in year 2 of the project.
  • DThe project pays back in year 3 of the project.

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    79% (19)
  • C
    13% (3)
  • D
    4% (1)