ISEB-BA1 · Question #96
Given the cashflows below, which of the following is correct?
The correct answer is B. The project does not pay back within the four year period. See the full explanation below for the reasoning.
Question
Given the cashflows below, which of the following is correct?
Exhibit
Options
- AThe project pays back in year 4 of the project.
- BThe project does not pay back within the four year period.
- CThe project pays back in year 2 of the project.
- DThe project pays back in year 3 of the project.