Which of the following would BEST be managed with the "keep satisfied" stakeholder management strategy?
The correct answer is B. Those with high power/influence and some interest in the project. See the full explanation below for the reasoning.
Question
Which of the following would BEST be managed with the "keep satisfied" stakeholder management strategy?
Options
- AThose with high power/influence and no interest in the project.
- BThose with high power/influence and some interest in the project.
- CThose with some power/influence and high interest in the project.
- DThose with some power/influence and some interest in the project.
How the community answered
(43 responses)- A9% (4)
- B84% (36)
- C5% (2)
- D2% (1)