A business case for a project claims that the new system will provide managers with more time to think creatively about strategic issues. What would this be classified as in a cost-benefit analysis?
The correct answer is C. An intangible benefit. See the full explanation below for the reasoning.
Question
A business case for a project claims that the new system will provide managers with more time to think creatively about strategic issues. What would this be classified as in a cost-benefit analysis?
Options
- AAn intangible cost.
- BA tangible benefit.
- CAn intangible benefit.
- DA tangible cost.
How the community answered
(25 responses)- A8% (2)
- B4% (1)
- C84% (21)
- D4% (1)