BCS-ISEB
ISEB-BA1 · Question #72
What are subsequent changes subject to once a requirements document has been signed off?
The correct answer is D. Requirements management. See the full explanation below for the reasoning.
Question
What are subsequent changes subject to once a requirements document has been signed off?
Options
- ARequirements verification.
- BRequirements documentation.
- CRequirements validation.
- DRequirements management.
How the community answered
(53 responses)- A15% (8)
- B8% (4)
- C4% (2)
- D74% (39)
Community Discussion