ISEB-BA1 · Question #21
A stakeholder in a project has been classified as having no interest but high power/influence on the power/interest grid. Which of the following would be an appropriate way of managing this…
The correct answer is B. Watch. See the full explanation below for the reasoning.
Question
A stakeholder in a project has been classified as having no interest but high power/influence on the power/interest grid. Which of the following would be an appropriate way of managing this stakeholder?
Options
- AIgnore.
- BWatch.
- CKeep on side.
- DKeep informed.
How the community answered
(50 responses)- A12% (6)
- B80% (40)
- C6% (3)
- D2% (1)