nerdexam
BCS-ISEB

ISEB-BA1 · Question #21

A stakeholder in a project has been classified as having no interest but high power/influence on the power/interest grid. Which of the following would be an appropriate way of managing this…

The correct answer is B. Watch. See the full explanation below for the reasoning.

Question

A stakeholder in a project has been classified as having no interest but high power/influence on the power/interest grid. Which of the following would be an appropriate way of managing this stakeholder?

Options

  • AIgnore.
  • BWatch.
  • CKeep on side.
  • DKeep informed.

How the community answered

(50 responses)
  • A
    12% (6)
  • B
    80% (40)
  • C
    6% (3)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full ISEB-BA1 Practice