What do the arrow headed lines between activities represent on a business activity model?
The correct answer is B. Logical dependency. See the full explanation below for the reasoning.
Question
What do the arrow headed lines between activities represent on a business activity model?
Options
- AActivity sequence
- BLogical dependency.
- CFunctional optionality.
- DFlow of data.
How the community answered
(32 responses)- A6% (2)
- B78% (25)
- C13% (4)
- D3% (1)