A company has been using an application for several years but one component still involves manual data entry. A project is started to automate this function that will impact several different…
The correct answer is C. Perform stakeholder analysis. See the full explanation below for the reasoning.
Question
A company has been using an application for several years but one component still involves manual data entry. A project is started to automate this function that will impact several different business units. What is the business analyst's (BA) first step in the project?
Options
- ASchedule a requirements workshop
- BModel the scope of the requirements
- CPerform stakeholder analysis
- DPrioritize the business requirements
How the community answered
(31 responses)- A10% (3)
- B3% (1)
- C84% (26)
- D3% (1)