IIA-CIA-PART2 · Question #278
Acceding to IIA guidance, which of the following statements is true regarding the risk assessment process performed by the internal audit activity?
The correct answer is C. The analysis should begin with ne identification of objectives. Option C is correct because IIA guidance establishes that identifying the organization's objectives is the foundational first step in risk assessment - you cannot meaningfully identify or evaluate risks without first understanding what outcomes are at stake. Option A is wrong…
Question
Acceding to IIA guidance, which of the following statements is true regarding the risk assessment process performed by the internal audit activity?
Options
- AThe assessment of high-level risks is typically a linear process.
- BManagement should create the preliminary risk matrix
- CThe analysis should begin with ne identification of objectives
- DLikelihood should receive greater consideration than impact
How the community answered
(37 responses)- A3% (1)
- C95% (35)
- D3% (1)
Explanation
Option C is correct because IIA guidance establishes that identifying the organization's objectives is the foundational first step in risk assessment - you cannot meaningfully identify or evaluate risks without first understanding what outcomes are at stake. Option A is wrong because the IIA describes the risk assessment process as iterative, not linear; it cycles back as new information emerges. Option B is wrong because it is the internal audit activity - not management - that creates the preliminary risk matrix, though management provides input and validation. Option D is wrong because IIA guidance treats likelihood and impact as co-equal factors; neither automatically outweighs the other in determining risk priority.
Memory tip: Use the acronym ORA - Objectives → Risks → Audit plan. You can't know what's at risk until you know what you're trying to achieve, so objectives always come first.