IIA-CIA-PART2 · Question #273
Which of the following risk assessment approaches involves gathering data from work team representing different levels of an organisation?
The correct answer is C. Facilitated team workshops. Facilitated team workshops are a risk assessment approach that involves gathering data from work teams representing different levels of an organization. This method encourages collaboration and open discussion among team members, allowing for a comprehensive identification and…
Question
Which of the following risk assessment approaches involves gathering data from work team representing different levels of an organisation?
Options
- ASurveys
- BManagement produced analysis 0
- CFacilitated team workshops
- DWeighted risk factors
How the community answered
(40 responses)- A8% (3)
- B3% (1)
- C88% (35)
- D3% (1)
Explanation
Facilitated team workshops are a risk assessment approach that involves gathering data from work teams representing different levels of an organization. This method encourages collaboration and open discussion among team members, allowing for a comprehensive identification and evaluation of risks from various perspectives within the organization. It helps in capturing a wide range of insights and facilitates consensus on risk priorities, making it a valuable tool for effective risk assessment.