nerdexam
IIA

IIA-CIA-PART2 · Question #173

IIA-CIA-PART2 Question #173: Real Exam Question with Answer & Explanation

Sign in or unlock IIA-CIA-PART2 to reveal the answer and full explanation for question #173. The question stem and answer options stay visible for context.

Question

Which of the following are advantages of flowcharts over internal control questionnaires? 1. Flowcharts reduce the need to test whether employees are observing internal control processes 2. Flowcharts provide a visual depiction of the processes in the area under review 3. Flowcharts identify and prioritize internal control design weaknesses. 4. Flowcharts highlight the control points to help internal auditors evaluate control design

Options

  • A1 and 3 only
  • B2 and 4 only.
  • C1.2. and 3 only
  • D
    1. 3 and 4 only

Unlock IIA-CIA-PART2 to see the answer

You've previewed enough free IIA-CIA-PART2 questions. Unlock IIA-CIA-PART2 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full IIA-CIA-PART2 Practice