nerdexam
IIA

IIA-CIA-PART2 · Question #167

IIA-CIA-PART2 Question #167: Real Exam Question with Answer & Explanation

Sign in or unlock IIA-CIA-PART2 to reveal the answer and full explanation for question #167. The question stem and answer options stay visible for context.

Question

At a construction company, an internal auditor is planning an audit of the company's process for designing and building grid connections The process involves customers making payments m three parts: - The first payment of 10% after approval of the customer s application - The second payment of 70% prior to construction - The third payment of 20% after construction is complete Which of the following key controls should the auditor test to ensure that the company is not taking any unwanted credit risks?

Options

  • AControls that ensure that grid connection design is finalized before construction is approved to
  • BControls that ensure construction orders are initiated after the second invoice is paid
  • CControls that ensure all three invoices are calculated correctly according to the total project cost
  • DControls that ensure that applications are verified for approval prior to initiating design and

Unlock IIA-CIA-PART2 to see the answer

You've previewed enough free IIA-CIA-PART2 questions. Unlock IIA-CIA-PART2 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full IIA-CIA-PART2 Practice