ICGB · Question #78
Which of these statements describe an undesirable situation when implementing SPC? (Note: There are 2 correct answers).
The correct answer is B. The Control Limits are wider than the customer specification limits E. Indication of the specification limits on the Control Chart. B is undesirable because when control limits are wider than specification limits, the process is statistically incapable - it will produce defects even while appearing "in control." This means the process naturally varies beyond what the customer will accept, and SPC alone…
Question
Which of these statements describe an undesirable situation when implementing SPC? (Note:
There are 2 correct answers).
Options
- AThe lower Control Limit for the R chart is equal to zero
- BThe Control Limits are wider than the customer specification limits
- CA process is in Statistical Control before implementation of SPC
- DAttempt to use SPC for tracking transaction times at a warehouse
- EIndication of the specification limits on the Control Chart
How the community answered
(37 responses)- A3% (1)
- B78% (29)
- C5% (2)
- D14% (5)
Explanation
B is undesirable because when control limits are wider than specification limits, the process is statistically incapable - it will produce defects even while appearing "in control." This means the process naturally varies beyond what the customer will accept, and SPC alone cannot fix an incapable process. E is undesirable because plotting specification limits directly on a control chart conflates two fundamentally different concepts: control limits reflect natural process variation (±3σ), while spec limits reflect customer requirements - mixing them encourages operators to tamper with a stable process or misjudge capability.
Why the distractors are wrong:
- A is normal - an R-chart LCL of zero is mathematically expected for small sample sizes (n ≤ 6, where D3 = 0), not a problem.
- C is actually desirable - you want a stable, in-control process as your baseline before implementing SPC so control limits are meaningful.
- D is acceptable - SPC works perfectly well for transactional/service metrics like time-based data; it's not limited to manufacturing.
Memory tip: Remember "two separate worlds" - the Control Chart world (process stability) and the Specification world (customer requirements). Any situation that merges these worlds is undesirable: either the process bleeds into spec territory (B) or specs bleed onto the chart (E).