Which statement(s) describe an undesirable situation when implementing SPC?

The correct answer is D. The Control Limits are wider than the customer specification limits. See the full explanation below for the reasoning.

Question

Which statement(s) describe an undesirable situation when implementing SPC?

Options

  • AThe lower Control Limit for the R chart is equal to zero
  • BAttempt to use SPC for tracking transaction times at a warehouse
  • CA process is in Statistical Control before implementation of SPC
  • DThe Control Limits are wider than the customer specification limits

How the community answered

(58 responses)
  • A
    7% (4)
  • B
    3% (2)
  • C
    16% (9)
  • D
    74% (43)