A Belt rearranged the location of the parts inventory for a rework station locating the most often used parts to be within hand reach of the repair person. This rearrangement resulted in quicker…

The correct answer is A. Motion. You've hit your session limit · resets 5:20pm (America/New_York)

Question

A Belt rearranged the location of the parts inventory for a rework station locating the most often used parts to be within hand reach of the repair person. This rearrangement resulted in quicker repair times by eliminating one of seven major elements of waste which is the Waste of __________.

Options

  • AMotion
  • BConveyance
  • CInventory
  • DWaiting

How the community answered

(54 responses)
  • A
    76% (41)
  • B
    4% (2)
  • C
    6% (3)
  • D
    15% (8)

Explanation