Which of the following activities comes under the `design' category of the business process management?
The correct answer is A. Identification of current business process. You've hit your session limit · resets 5:20pm (America/New_York)
Question
Which of the following activities comes under the `design' category of the business process management?
Options
- AIdentification of current business process
- BIntroduction of different variables for the designs
- CEvaluation of actual performances of the processes
- DExtraction of data related to the performances of the processes
How the community answered
(26 responses)- A85% (22)
- B4% (1)
- C8% (2)
- D4% (1)
Explanation
You've hit your session limit · resets 5:20pm (America/New_York)