Six_Sigma
ICBB · Question #313
Which of the following process flow metrics is an essential requirement to calculate `productivity'?
The correct answer is A. Effort-related metrics. You've hit your session limit · resets 5:20pm (America/New_York)
Question
Which of the following process flow metrics is an essential requirement to calculate `productivity'?
Options
- AEffort-related metrics
- BDefect-related metrics
- CCost-variation metrics
- DSchedule slippage metrics
How the community answered
(39 responses)- A77% (30)
- B13% (5)
- C5% (2)
- D5% (2)
Explanation
You've hit your session limit · resets 5:20pm (America/New_York)
Community Discussion
No community discussion yet for this question.